2025About $148,000 collected on change work that never got billed
The result
About $310,000 in possibly unbilled work turned up. About $175,000 in added billings got approved.
How it worked
A midsize general contractor was busy, and several finished jobs still came in with disappointing margins. Management blamed estimating or material prices. We went through Procore change orders, RFIs, field directives, superintendent reports, subcontractor invoices, project emails and Sage job-cost records. AI caught references to extra work, owner-directed changes and field conditions that showed up in correspondence but had no approved change order or bill behind them. That came to about $310,000 in possibly unbilled work. The contractor confirmed entitlement, documentation and notice on each item, got about $175,000 in additional billings approved, and collected about $148,000.